Revised Summary and Scope of Work

Repair Description

 
LL11 Repairs
Roof Replacement
Roof Railing
Windows Replacement including ACM removal
Electrical Panel Replacement - Apts
Replace Elevators
Contingency including mobilization, General Conditions, insurance, Bond, etc.
Estimated
Cost

 
$ 11,600,0000
$ 6,400,000
$ 1,600,000
$ 20,500,000
$ 1,662,000
$ 6,900,000
$ 2,000,000
Estimated
Cost Saving

 
$ -
$ -
$ -
$ -
$ -
$ -
$ -
Potential Health
Benefit

 
None
None
None
None
None
None
Urgency

 
Short Term (<12 months)
Critical
Critical
Long Term (1 to 15 years)
Critical
Short Term (<12 months)